A solid foundation for digital infrastructure
Cloud computing, artificial intelligence and rapidly growing volumes of data require high-performance data centres. Their expansion is intended to drive the economic development of new technologies and strengthen the digital sovereignty of Germany and Europe. As part of the AWS European Sovereign Cloud, the tech giant Amazon Web Services is currently building several large-scale data centres. One of the new digital hubs is being built near Finsterwalde in southern Brandenburg. Even before the actual construction project began, extensive site preparation was required. The ground on which the data centre is to be built had to be raised, and the site levelled to the planned height. REMEX was responsible for coordinating the procurement and delivery of the building materials, as well as the associated material flow management.
Planned data centres in Berlin/Brandenburg, as at August 2026
(Source: tagesschau.de)
Amazon Web Services (AWS) large-scale data centre
One of the large-scale data centres is being built in the Massen-Niederlausitz commercial and industrial park near Finsterwalde as part of the AWS European Sovereign Cloud. The cloud solution will be operated within the European Union and is technically separated from the global AWS network. It will be managed from Potsdam under German control structures.
Area
Power
Part of the European Sovereign Cloud
Start of construction February 2026
High material requirements – a logistical challenge
Given the size of the construction site, large quantities of suitable building materials were required. As there was insufficient recycled material available in the immediate vicinity, the contractor opted for a mixture of materials with a grain size of 0–32 mm based on greywacke. This rock offers the necessary load-bearing capacity and could be sourced from regional quarries in Brandenburg and Saxony-Anhalt. However, the challenge for REMEX lay not only in the total quantity. The material had to be supplied on a just-in-time basis and transported continuously to the construction site. To achieve this, material availability, transport capacity and construction progress had to be precisely coordinated.
117,000 tonnes of material for site levelling
Between June and September 2026, a total of 117,000 tonnes of mineral construction material was moved, with up to 3,000 tonnes on peak days. A haulage network comprising around 50 lorries was deployed for this purpose. Given the volume of material, close coordination between suppliers, the haulage contractor and the site management was essential. REMEX integrated the individual processes into a reliable supply chain and kept a close eye on material availability and transport logistics at all times. The site was levelled on schedule and without any logistics-related bottlenecks.
A reliable partner for challenging infrastructure projects
Whether industrial parks, transport infrastructure or data centres: large-scale projects place high demands on the availability of building materials and on logistics. Ensuring everything runs smoothly relies on the coordination of all parties involved. The project in Finsterwalde demonstrates how REMEX delivers challenging infrastructure projects with bespoke, one-stop solutions: reliable, efficient and precisely tailored to the project’s specific requirements.
Key logistical numbers
The project in Finsterwalde demonstrates how REMEX enables the timely delivery of challenging infrastructure projects through efficient material flow management and precise logistics.